We are writing to provide you with a brief update on the ELOR infrastructure project.

The Outer Ring Road advanced junction works at both the A6120/A61/Scott Hall Road and A6120/Roundhay Park Lane were substantially completed late 2019. The Councils Parks & Countryside landscape team are currently on site completing a number of hard and soft landscaped areas which will include the planting of over 300 additional trees.

The latest drone footage of these junction improvements can be found via this link https://youtu.be/ma5uhayoBt8

Contrary to reports, the main ELOR scheme has not commenced on site however the Council in partnership with Balfour Beatty are progressing a number of mitigation tasks including;

  • Installation of tree protection fencing & sections of boundary fencing
  • Completion of ecology surveys
  • Commencement of archaeological surveys site wide
  • Hedgerow/tree clearance
  • Programme coordination with third parties
  • Continuation of demolition of the Redhall Nursery site

Further updates will be provided in the coming weeks in relation to the formal commencement of the main scheme.

If you have any queries regarding the above information please contact our Public liaison, Social Value and Educational Skills coordinator, Cherie Paterson on 07547936099 or email: elor@leeds.gov.uk

If you would like to be kept informed of up to date information regarding the project, please visit our website at www.elor.uk and sign up for email updates and monthly newsletter.  The ELOR Project Offices at Ring Road, LS17 8NJ, are open between 9am and 3pm Monday to Friday, where project staff are on hand to answer any questions you may have if you would like to visit us in person.

Yours faithfully,

The ELOR Project Team